Proposition 218 Election
The Consolidated Irrigation District (CID) was created over 100 years ago with one purpose: to serve agricultural producers — delivering water to your fields, protecting surface water rights, and helping to keep this region farming. Today, landowners know better than anyone that farming in California is getting harder, and the future feels increasingly uncertain.
CID is committed to standing with farmers, fighting to protect your ability to farm. That commitment now requires further investment in District facilities – that is why we proposed an increase of our current assessment through a Proposition 218 election. Through the election, CID aims to secure additional water supply, safeguard your farming operation, and protect the future of farming in our region.
Proposition 218 Election Results
On August 5, 2025 the Proposition 218 election passed with 66% of votes approving the proposed increased assessments. The CID Board of Directors set the 2026 assessment at $74 per acre for CID Gravity, which is the majority land classification for parcels in CID. Landowners can learn more about CID’s land classifications and associated assessments below.
Although the election is over, the District’s engagement with landowners will continue. In the coming months, CID plans to consider new basin locations and identify maintenance opportunities for aging infrastructure. The District will also continue applying for grant funding.
CID thanks landowners for their participation in the Proposition 218 process. CID remains committed to standing with farmers, fighting to protect your ability to farm. CID encourages stakeholders to stay engaged as the District takes steps toward a more sustainable future.
Proposition 218 Election Resources
An Investment to Increase Water Supplies Within the District
The District held a Proposition 218 election to raise assessments largely to follow through on our local commitments to implement the Sustainable Groundwater Management Act (SGMA). Signed into law in 2014, SGMA requires groundwater basins to achieve groundwater sustainability by 2040.
CID is responsible for addressing the groundwater overdraft that is occurring in our District each year. In the early days of SGMA, overdraft was estimated to be approximately 15,000 acre-feet on average per year. But with more recent data and reports, overdraft is currently estimated to be closer to 40,000 acre-feet as a result of conversion to high-value permanent crops with higher water demand.
The Plan: Develop Additional Water Supply
There are two ways to address overdraft – increase water supply, or decrease water demand. CID’s plan is to focus on increasing supply by building infrastructure to capture up to 100,000 acre-feet of additional floodwater during wet years. This would add an estimated 40,000 acre-feet of new water supply to the District on an annual basis, for the benefit of landowners.
Instead of letting excess Kings River floodwater pass us by, it can be put to use right here in CID. But funding is needed to construct infrastructure and the projects needed to make this possible. Additional revenue through increased assessments would fund building more recharge basins, improving CID’s conveyance system, and increasing CID’s Kings River diversion capacity.
Approved Assessments
| Assessment Classification | Current Assessment | Year 1 (2026) Approved Assessment | Proposed Max Assessment* |
| CID Gravity | $53.00/acre | $74.00/acre | $126.00/acre |
| Pump | $22.00/acre | $31.00/acre | $53.00/acre |
| Church Gravity | $64.00/acre | $89.00/acre | $151.00/acre |
| Pond | $0.50/acre | $0.50/acre | $0.50/acre |
| Free Water | $22.00/acre | $22.00/acre | $22.00/acre |
While the Board is authorized to approve an assessment up to the maximum proposed amount, the amount assessed will be set each year by the District’s Board of Directors, based on actual budget needs identified in the annual budget. The Board does not intend to impose the maximum assessment in the first year.
Classification descriptions:
CID Gravity – users that receive surface supplies
Church Gravity – select users eligible to receive surface supplies through the Lone Tree Canal system and receive a longer duration of surface water deliveries
Pump – users that are not eligible to receive surface supplies
Pond – farmlands that are periodically used for recharge operations by the District
Free Water – lands that have historic water rights to receive water apart from the rights or contracts held by CID
Comparing the Cost of Sustainability under SGMA
The graphic below illustrates the costs to farm under groundwater allocation programs in nearby basins, versus what CID has approved through its assessment increase. It compares what it would be like to farm a 20-acre, groundwater-dependent vineyard, assuming an annual 2.3 acre-feet per acre water demand.
Consolidated Irrigation District
Farm 20 Acres
Fallow 0 Acres
CID Gravity annual fees: $2,520
Pump annual fees: $1,060
Mid Kaweah GSA
Farm 12 Acres
Fallow 8 Acres
$3,364
East Kaweah GSA
Farm 13.5 Acres
Fallow 6.5 Acres
$7,500
Madera County GSA (Madera Subbasin)
Farm 9.2 Acres
Fallow 10.8 Acres
$250
Madera County GSA (Delta-Mendota Subbasin)
Farm 6.2 Acres
Fallow 13.8 Acres
$4,350
Westlands Water District GSA
Farm 5.2 Acres
Fallow 14.8 Acres
$12,000
The Bottom Line:
The approved assessments provides the funding needed for CID to build infrastructure and capture more flood water. While no one can predict future weather conditions, CID is doing everything it can to avoid landowners having to fallow land because of pumping restrictions. This plan gives us the best chance to protect farming in the area and avoid the unknowns of State intervention.
Benefits
Protect Land Values
A 2024 farmland values analysis states, “…districts with better water security managed to cushion the blow of market fluctuations, whereas those with precarious water access faced sharper declines in land values. This pattern underscores the critical influence of water availability on agricultural viability and the potential for water management strategies to mitigate adverse economic impacts” (Farmland Values: The California Report).
To protect property investments, CID is pursuing additional water supply through new assessments. This effort helps ensure land within the District remains among the most valuable in the Valley.
More Certainty About the Future Under SGMA
The Prop 218 rates and the benefits are known: building additional basins, improving conveyance infrastructure, and increasing diversion capacity off the Kings River. This plan provides more certainty compared to the unknowns of groundwater allocations and State intervention. Local control gives us the opportunity to shape our future, rather than having it handed down by the State.
Protect Water Rights
Investing in legal protections and water rights defense is essential to safeguarding CID’s long-term water supply. There are multiple parties after our Kings River water rights, and the District is actively fighting against these threats. As competition for water increases under SGMA, protecting these rights from current and future legal challenges is critical to ensuring a reliable supply for our growers.
Develop Additional Water Supply
With new investments funded by the proposed assessments, we can build the facilities needed to take full advantage of wet-year flows including conveyance, basins, and diversion points off the Kings River.
Thank you for attending a public workshop
landowners attended a public workshop to learn more about the election and have their questions answered.
Public Workshop #1
June 3, 2025, 1:00 PM – 2:30 PM
Kearney Ag Research and Extension Center
9240 S Riverbend Ave, Parlier, CA 93648
Public Workshop #2
June 19, 2025, 1:00 PM – 2:30 PM
Caruthers Fair Grounds
13599 S Raider Ave, Caruthers, CA 93609
The Public Hearing took place on August 5, 2025 at 10:00 AM at the Kearney Ag Center, 9240 S Riverbend Ave, Parlier, CA 93648.
Ballots must be received prior to the conclusion of the public input portion of the hearing on August 5th.
Latest Projects
Since the 2018 Proposition 218, the District has followed through on projects and SGMA work – over 210 acres of groundwater recharge basins have been built, and 120 acres of additional groundwater recharge basins are currently in progress. The District also led efforts to develop a State-approved Groundwater Sustainability Plan, one of the few critically overdrafted subbasins in the state to receive approval. This was a significant milestone for maintaining compliance with SGMA’s requirements, and therefore keeping local control within the Kings Subbasin.
Did you know? Consolidated has been successful in receiving outside funds for projects to make landowner assessments stretch further. Since 2020, we’ve received $8.7 million in funds to build groundwater recharge projects. The District plans to continue to pursue funding to offset the landowner cost burden by keeping the land-based assessments as low as possible.
Groundwater Recharge Basins Built Since 2020
Nebraska and Walnut Basin
Temperance Mtn View
Huntsman
Central Bethel
Adams and Academy Recharge Basin
Contact Us
If you have any questions or would like to discuss the Proposition 218 election, please don’t hesitate to reach out. You can email us at info@cidwater.com or call (559) 896-1660.