FAQ

FAQs

Election Background

Our current assessment does not generate enough revenue to cover Consolidated Irrigation District (CID) costs — especially with new challenges we are facing under SGMA. The District is proposing to increase its current assessment through a Proposition 218 election. Increased revenue will allow the District to fulfill its plans to capture up to an additional 100,000 acre-feet of surface water during flood years to offset groundwater pumping and support the long-term viability of farming in the area.

Proposition 218 elections require the support of voters, District landowners, to allow the District to increase land-based assessments. In this case, the proposed assessments will fund activities that improve infrastructure, increase water supply capture, and help protect Kings River water rights. You are being asked to vote on whether to approve an increase to your District assessment.

The District plans to build new groundwater recharge basins, improve and maintain its conveyance infrastructure, protect our Kings River water rights, and increase diversion capacity from the Kings River to help ensure flood water does not run past us during wet years. This investment is critical to meet our Sustainable Groundwater Management Act (SGMA) obligation to balance and stabilize groundwater overdraft by 2040.

Since the 2018 Proposition 218, the District has followed through on its commitments – over 210 acres of groundwater recharge basins have been built, and 120 acres of additional groundwater recharge basins are in progress. The District also led efforts to develop a State-approved Groundwater Sustainability Plan, one of the few critically overdrafted subbasins in the state to receive approval. In the early days of SGMA, our overdraft estimate was 15,000 acre-feet on average per year. But with more recent data and reports, that number has jumped up to 40,000 acre-feet of estimated overdraft, as crop demands have increased. To address the problem, we can either limit demand or increase supply. Our approach is to develop infrastructure through these proposed increased assessments so we are not stuck with demand reduction (groundwater allocations) as our primary option.

Proposed Assessments

Assessment ClassificationCurrent AssessmentProposed Max Assessment*Year 1 (2026) Planned Assessment
CID Gravity$53.00/acre$126.00/acre$74.00/acre
Pump$22.00/acre$74.00/acre$31.00/acre
Church Gravity$64.00/acre$151.00/acre$89.00/acre
Pond$0.50/acre$0.50/acre$0.50/acre
Free Water$22.00/acre$22.00/acre$22.00/acre

While the Proposition 218 election passing would authorize the Board to approve an assessment up to the maximum proposed amount, the amount assessed will be set each year by the District’s Board of Directors, based on actual budget needs identified in the annual budget. The Board does not intend to impose the maximum assessment in the first year.

The proposed assessments were developed through an independent engineering study and preparation of an Engineer’s Report. The District’s Board of Directors and staff evaluated the proposed assessments outlined in the Engineer’s Report. You can view the Engineer’s Report on the District’s Proposition 218 website at cidwater.com/prop218election.

Potential Election Outcomes

Protect Land Values – The District plans to increase average annual water supply by 40,000 acre-feet.

More Certainty About the Future under SGMA – The Prop 218 rates and the benefits are known: building additional basins, improving conveyance infrastructure, and increasing diversion capacity off the Kings River. This plan provides more certainty compared to the unknowns of groundwater pumping restrictions and State intervention.

Protect Water Rights – Funding to defend against those who want to limit our water rights.

Maximize and Expand Water Capture Capacity – With new investments funded by the proposed assessments, we can build the facilities needed to take full advantage of wet-year flows including conveyance, basins, and diversion points off the Kings River.

If the election were to fail there would be limited funding and the District must consider:

  • – Losing out on available flood water supplies without enough infrastructure to capture it
  • – Groundwater restrictions to fix our current overdraft and comply with SGMA
  • – Higher risk of State Water Resources Control Board intervention to manage groundwater for us if we cannot fix the problem locally

The election will pass if a majority of the votes returned are in favor of the proposed assessment increase (50%+1). Votes are weighted by acreage, correlating to the financial obligation of the affected property per acre.

Our goal is to avoid or delay the need to impose a groundwater allocation. We believe the proposed assessment will position us to meet key SGMA sustainability milestones, including reducing 30% of our overdraft by 2030. While we cannot control hydrologic conditions and cropping decisions that impact water demand, we believe this is our best shot at keeping allocations at bay. It is important to note the District is estimating future flood water capture potential based on what has happened in the past (historical Kings River flood release conditions). But hydrology is variable, and no one can control whether a longer series of dry years occurs and warrants demand reduction to stay on track with SGMA milestones. The District wants to maintain as much flexibility as possible for landowners to farm under SGMA, so even if pumping restrictions were to become necessary in a drought, investments in surface water supplies would mean a less restrictive pumping requirement.

Groundwater Sustainability

The District has been successful in receiving grant funding for SGMA projects. Since 2020, the District has received $8.7 million in funds to build groundwater recharge projects. The District plans to continue to pursue funding to offset the landowner cost burden by keeping the land-based assessments as low as possible.

While all options are on the table, District owned and operated groundwater recharge basins offer a reliable place to park water quickly. Rarely do we have long lead times to plan for a flood release, and the timing of flood releases is not always optimal for cropped land. About 60% of the total annual flood water available occurs in May through June, a time where flooding a field could risk crop health.

The rate of recharge we get with the sandy soils within the District makes groundwater recharge basins exceptionally efficient – we can capture high volumes in a short period of time. We can sink one acre-foot per acre per day with our sandy soils. If we had an additional 1,000 acres of groundwater recharge basins, we could recharge 1,000 acre-feet per day. During a 100-day flood release, that is approximately 100,000 acre-feet recharged on just 1,000 acres – an extremely efficient use of that land and space.

Voting and More Resources

All landowners will receive a Proposition 218 ballot and public hearing notice in the mail in May. To vote, thoroughly fill out your Proposition 218 ballot and submit it in one of three ways:

  1. Mail your ballot in the pre-paid postage envelope provided in the ballot packet,
  2. Bring your ballot to the District’s Public Hearing on August 5, 2025 at 10:00 AM, or
  3. Drop your ballot off at the secure ballot box during office hours between 8:00 AM – 5:00 PM at the District’s office, 2255 Chandler Street, Selma, CA 93662.

Ballots must be received prior to the conclusion of the public input portion of the hearing on August 5th. To request a replacement ballot, landowners must call (209) 259-6740 or ask for one at the public hearing.

If the Proposition 218 election passes, the Board of Directors will determine the assessment amount for the 2026 fiscal year budget during the August Board meeting. Assessments will be collected in fall 2025 and spring 2026 through each County’s property tax bills. This is in preparation for the District’s 2026 fiscal Year, which begins January 1, 2026.

Visit the District’s Proposition 218 webpage at cidwater.com/prop218election to find more information and resources, including an educational handout, a copy of the mailers, and the Engineer’s Report. You may also contact us by email at info@cidwater.com or call (559) 896-1660.